Project Management Professional (PMP) — Question 1097

A lead project manager for an agile project needs to prioritize requirements, define the scope of the initial product, and deliver the approved scope in a series of multiple versions. What should the project manager do next?

Answer options

Correct answer: C

Explanation

The correct answer is C because collaborating with the product owner ensures that the requirements are evaluated and prioritized based on customer needs and business value. Option A, while beneficial for understanding value, does not directly address prioritization. Option B relies on the developer rather than the product owner, which is not ideal in an agile context. Option D may lead to prioritization based on politics rather than actual project needs.