Project Management Professional (PMP) — Question 1096

A defect is identified during user acceptance testing that could significantly impact the system's performance. The project team has advised that this defect puts the delivery date at risk.

Which risk management process should be performed?

Answer options

Correct answer: C

Explanation

The correct answer is C, as planning risk responses is essential to define strategies for mitigating the system performance issue. Options A and D focus on analyzing risks rather than addressing them, while option B is about monitoring existing risks rather than planning responses.