Project Management Professional (PMP) — Question 1092
A project manager is assigned to a dental equipment development project that is in the middle of its design phase. After reviewing the project prototype, it is identified that a couple of requirements specifications are missing.
Which action should the project manager take next?
Answer options
- A. Ask the team to wait until they are able to update the requirements specifications.
- B. Discuss with the team and build a workaround plan to immediately deliver the pending requirements specifications.
- C. Meet with the development team to review and assess the requirements specifications.
- D. Prepare a change request for the change control board (CCB) to remove the missing requirements specifications.
Correct answer: C
Explanation
The correct answer is C because meeting with the development team allows the project manager to review and clarify the missing requirements specifications, ensuring that the project stays on track. Option A is incorrect as pausing the team delays progress, while option B focuses on workarounds instead of addressing the root issue. Option D is wrong because removing the missing specifications is not a valid solution; they need to be identified and addressed.