Project Management Professional (PMP) — Question 1086

A project manager arranged a team-building activity to build and maintain teamwork, trust, and commitment due to internal team conflicts. Two months after completing the training, another situation is causing new delays in the project.

What should the project manager do to address this concern?

Answer options

Correct answer: D

Explanation

The correct answer is D because the project manager needs to reassess the new issues affecting the team to find an effective solution. Options A and B do not directly address the underlying problems within the team, while option C focuses on communication rather than on actionable steps to resolve the conflicts.