Project Management Professional (PMP) — Question 1085

A project manager has been managing an agile project for 6 months. Over the last two iterations, the team velocity has decreased due to a new technology that was needed for the product.

What should the project manager do to continue with the delivery plan and return to the expected velocity?

Answer options

Correct answer: C

Explanation

The correct answer is C, as using retrospectives allows the team to analyze the effects of the new technology and identify necessary adjustments to skills. Option A may not address the root cause, while B could disrupt team dynamics, and D, although useful, does not directly tackle the issue of the team's velocity with the new technology.