A new project manager has been assigned to an environmental project. After reviewing the project plan, the project manager notices that health and safety requirements have not been properly addressed. This is a serious concern, and the project manager wants to fix this issue immediately.

Why is this situation problematic?

Answer options

Correct answer: D

Explanation

This situation is problematic because the project manager is legally required to comply with the regulatory requirements of the project location, as stated in option D. Failure to address health and safety could lead to serious legal repercussions and project delays, which are highlighted in option B, but the primary issue is the legal obligation. Options A and C, while important, do not directly address the immediate concern of compliance with health and safety regulations.