Project Management Professional (PMP) — Question 1053
Upon analyzing the report requirements to create a functional design, the project team finds that the information source is not correct and needs to be adjusted. What should the project manager do?
Answer options
- A. Initiate a change request procedure.
- B. Build a prototype to verify the information.
- C. Consult with subject matter experts (SMEs).
- D. Review the statement of work (SOW).
Correct answer: A
Explanation
The correct answer is A, as initiating a change request procedure is necessary when there are discrepancies in project requirements. Options B, C, and D do not directly address the need for formal changes to be made to the project scope or requirements, which makes them less suitable in this context.