Project Management Professional (PMP) — Question 1044

A bridge construction project has been paused due to a political change in the local government. After almost 5 years, the new government would like to resume the project, and a project manager is assigned.

What should the project manager do first?

Answer options

Correct answer: D

Explanation

The correct answer is D because examining the project's business case provides essential insights into its viability and alignment with current objectives. This step is critical to ensure that the project is still relevant and justified before moving forward. While the other options are important, they are secondary to confirming the project's business case.