Project Management Professional (PMP) — Question 1031

A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more information to be shared.

What should the project manager do next?

Answer options

Correct answer: D

Explanation

The correct answer is D because scheduling a meeting allows the project manager to gather detailed insights about the stakeholder's concerns and requirements. Options A and B do not directly address the stakeholder's dissatisfaction, while option C dismisses the stakeholder's immediate needs by delaying communication.