Project Management Professional (PMP) — Question 1031
A project manager joins an existing project. One project stakeholder is unhappy with the frequency and types of project updates received and has made a request for more information to be shared.
What should the project manager do next?
Answer options
- A. Consult the scope baseline document to track project updates.
- B. Update the project communications management plan immediately.
- C. Inform the stakeholder to wait for the annual stakeholder review meeting.
- D. Schedule a meeting with the stakeholder to better understand their request.
Correct answer: D
Explanation
The correct answer is D because scheduling a meeting allows the project manager to gather detailed insights about the stakeholder's concerns and requirements. Options A and B do not directly address the stakeholder's dissatisfaction, while option C dismisses the stakeholder's immediate needs by delaying communication.