As a project is reaching completion, the project sponsor tells the project manager to immediately close the project and to move on to another project. Which critical task should the project manager complete before closing the project?

Answer options

Correct answer: B

Explanation

The correct answer is B because archiving project documents is essential for knowledge transfer and future reference in subsequent projects. Options A and C, while important, do not take precedence over the need to properly archive documentation. Option D does not address the immediate task of closing the project.