Project Management Professional (PMP) — Question 1015

A team is entering into a forming stage after kickoff, with project objectives identified and team members assigned with roles and responsibilities. However, during the team meetings, a team member does not agree on project documents and makes comments that could affect the performance of other team members.

What should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because establishing ground rules collaboratively helps to create a shared understanding and fosters a positive team environment. Option B is not effective as it encourages isolation rather than collaboration. Option C may escalate the situation unnecessarily, while option D does not actively address the disruptive behavior.