A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.
Which distribution list should the project manager use when sending out invitations?
Answer options
- A. Team members, consultants from outside the project with experience in the field, and the customer
- B. Functional managers, team members, and external consultants with experience in the field
- C. Weather experts, functional managers, and team members
- D. Team members, engineers, and weather experts
Correct answer: A
Explanation
Answer A is correct because it includes team members, experienced external consultants, and the customer, all of whom are crucial for identifying risks. The other options either omit key stakeholders or include individuals who may not contribute relevant insights for the project risks.