Project Management Professional (PMP) — Question 1002

A project team is identifying project risks for a bridge to be built across a river. The team needs to send out invitations for a risk workshop to better understand the risks involved.

Which distribution list should the project manager use when sending out invitations?

Answer options

Correct answer: A

Explanation

Answer A is correct because it includes team members, experienced external consultants, and the customer, all of whom are crucial for identifying risks. The other options either omit key stakeholders or include individuals who may not contribute relevant insights for the project risks.