Project Management Professional (PMP) — Question 1001

A hybrid project has just started, which will result in a new technology that could disrupt the market if well accepted by the public. The product requires health and safety approvals from the government. As this is an innovative solution, the sponsor and product owner are unsure if it will be accepted by the public.

What is the appropriate flow for product development?

Answer options

Correct answer: B

Explanation

The correct answer is B because focusing on must-have functionalities allows for rapid prototyping, enabling the team to receive early feedback and make necessary adjustments. Option A delays feedback until the entire product is complete, which could lead to greater risks if the product is not well received. Option C limits stakeholder engagement to only internal parties, missing valuable external insights, while Option D postpones critical government interaction until after development, which may hinder approval processes.