PMI Scheduling Professional (PMI-SP) — Question 57

You work as a project manager for BlueWell Inc. Which of the following plans will you use to define how resources are brought onto the project team, how they are managed while on the project team, and how they may be released from the project team?

Answer options

Correct answer: B

Explanation

The correct answer is B, the Project Staffing Management Plan, as it specifically focuses on how to acquire, manage, and release project team members. Option A pertains to scheduling tasks rather than resource management, C addresses broader human resources aspects, and D deals with communication strategies, none of which directly address staffing needs.