PMI Scheduling Professional (PMI-SP) — Question 55

Which of the following is an output of the Identify Stakeholders process?

Answer options

Correct answer: D

Explanation

The Stakeholder Register is the correct answer because it is specifically produced during the Identify Stakeholders process, documenting all identified stakeholders. The other options, such as the Scope baseline, Project scope statement, and Project charter, are outputs of different processes within project management and do not pertain to stakeholder identification.