PMI Scheduling Professional (PMI-SP) — Question 52
You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start-to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?
Answer options
- A. Project management overhead
- B. Hammock activity
- C. Subproject
- D. Finish-to-Start
Correct answer: B
Explanation
The correct answer is B, Hammock activity, which refers to a type of activity that spans across multiple tasks and is used to represent the effort required for managing resources or equipment. The other options do not accurately describe this concept; A refers to general project management costs, C denotes a smaller project within a larger one, and D is a different type of dependency relationship.