PMI Scheduling Professional (PMI-SP) — Question 51

You are the project manager for your organization. You are working through the control schedule process. According to the PMBOK, there are four inputs to this process. Which one of the following is NOT an input to the control schedule process?

Answer options

Correct answer: A

Explanation

The correct answer is A, as 'Schedule data' is not categorized as an input in the control schedule process. The other options, including 'Work performance information,' 'Project management plan,' and 'Project schedule,' are all recognized inputs that provide essential information for monitoring and controlling the schedule.