PMI Scheduling Professional (PMI-SP) — Question 37

Once the project's WBS has been created what process may happen next?

Answer options

Correct answer: B

Explanation

The correct answer is B, as defining activities is the next logical step following the creation of the WBS. This process involves identifying the specific tasks that need to be performed to achieve project objectives. The other options are also important processes in project management but occur after the activities have been defined.