PMI Scheduling Professional (PMI-SP) — Question 36
Thomas works as a contract-based project manager for BlueWell Inc. Management has hired Thomas to manage a high-risk project because Thomas has years of experience with this technology and similar project. Thomas would like to use his own templates for the project schedule, quality, and risk management approach. Management is fine with this, except after reviewing the template they had preferred Thomas to use 24-hour time periods for his project calendar rather than the 8-hour time periods as indicated. Thomas agrees, but now he has to update what document in his project management plan?
Answer options
- A. Project calendar
- B. Activity attributes
- C. Resource calendar
- D. Schedule management plan
Correct answer: A
Explanation
The correct answer is A, Project calendar, because the management's request specifically pertains to the format of the time periods used in the project calendar. The other options, such as Activity attributes, Resource calendar, and Schedule management plan, do not directly relate to the time format adjustments that Thomas needs to make.