PMI Risk Management Professional (PMI-RMP) — Question 95

A project manager is running a high-cost telecommunications project. There is a monthly status meeting, and the risk manager should provide an update to the project team and project sponsors on major risks.
What risk related information should be included in the monthly status meeting of this complex project?

Answer options

Correct answer: D

Explanation

The correct answer is D because it includes the most relevant risk information: current top priority risks, any risks that have occurred, and those that have been closed in the last period. Options A, B, and C either omit important aspects of risk management or include irrelevant details that do not align with the focus of the meeting.