PMI Risk Management Professional (PMI-RMP) — Question 94
The feasibility of the risk management planning is dependent upon which of the following aspects of the organization?
Answer options
- A. Competitive market share
- B. Level of risk management maturity
- C. Alignment with industry standard requirements
- D. Culture, people and infrastructure capabilities
Correct answer: D
Explanation
The correct answer is D because the culture, people, and infrastructure capabilities of an organization determine how effectively it can implement and sustain risk management practices. While the other options may impact risk management in different ways, they do not directly influence its feasibility as much as the internal aspects represented by option D.