PMI Risk Management Professional (PMI-RMP) — Question 78

A project manager is developing the risk management process and schedules a risk planning workshop at the start of the project. Upon receiving the invitation, a senior stakeholder emails the project manager stating that a risk management plan is not needed since this is a small project, and lack of a plan will reduce costs.
Which of the following should the project manager do?

Answer options

Correct answer: A

Explanation

The correct answer is A because risk management is essential for all projects, regardless of size, and helps identify potential issues proactively. Option B is incorrect as cancelling the workshop undermines the risk management process. Option C is not advisable because involving all relevant stakeholders is crucial for effective risk management. Option D misallocates focus by attempting to cut costs elsewhere instead of addressing the importance of risk management.