The stakeholder is unwilling to make decisions that would result in negative consequences to the project. Which of the following describes the stakeholder's attitude regarding project risks?
Answer options
- A. Risk averse
- B. Risk neutral
- C. Risk accepting
- D. Not enough information available to describe the stakeholder's risk attitude
Correct answer: A
Explanation
The correct answer is A, as a risk-averse stakeholder avoids decisions that could lead to negative impacts on the project. Options B and C are incorrect because a risk-neutral stakeholder would not prioritize avoiding risks, and a risk-accepting stakeholder would be willing to face risks. Option D is not applicable since the stakeholder's attitude is clearly described.