PMI Risk Management Professional (PMI-RMP) — Question 7

During what process should a project manager assign a risk owner?

Answer options

Correct answer: D

Explanation

The correct answer is D, as risk owners are typically assigned during the Identify Risks process to ensure accountability and management of specific risks. The other options involve planning responses or management strategies but do not focus on the assignment of ownership for identified risks.