During what process should a project manager assign a risk owner?
Answer options
- A. Plan Risk Responses
- B. Plan Risk Management
- C. Monitor Risks
- D. Identify Risks
Correct answer: D
Explanation
The correct answer is D, as risk owners are typically assigned during the Identify Risks process to ensure accountability and management of specific risks. The other options involve planning responses or management strategies but do not focus on the assignment of ownership for identified risks.