PMI Risk Management Professional (PMI-RMP) — Question 6
Which of the following represents the best description of the role of project manager for project risk management?
Answer options
- A. Determining the acceptable levels of risk for the project in consultation with stakeholders, approving the risk management, assessing the impact of proposed scope changes
- B. Determining the acceptable levels of risk for the project in consultation with stakeholders, approving the project management plan, participating in all aspects of the project risk management process
- C. Approving the risk management plan, participating in all aspects of the project risk management process, auditing the risk management processes in the project
- D. Determining the acceptable levels of risk for the project in consultation with stakeholders, approving the risk management plan, participating in all aspects of the project risk management process
Correct answer: D
Explanation
The correct answer, D, describes the comprehensive role of a project manager in risk management, including stakeholder consultation and participation in all related processes. Options A and B incorrectly reference approving the risk management plan instead of specifying its endorsement, while C lacks the crucial aspect of determining acceptable risk levels in consultation with stakeholders.