PMI Risk Management Professional (PMI-RMP) — Question 61
The project sponsor asks the project manager about the accuracy of the project data. The project manager realizes that some risks have not been updated recently.
What should the project manager do regarding those risks?
Answer options
- A. Review the assumptions analysis
- B. Create a risk response plan for those risks
- C. Review the risk register to check for the new risks
- D. Conduct a checklist analysis on each risk
Correct answer: A
Explanation
The correct answer is A, as reviewing the assumptions analysis helps identify any outdated or incorrect assumptions associated with the risks. The other options focus on different aspects of risk management, such as creating plans or checking for new risks, but do not directly address the need to ensure the accuracy of current risk data.