PMI Risk Management Professional (PMI-RMP) — Question 60
After a number of risk workshops, risks have been identified. Which is the first element the risk owner should look for in risk response plan to help mitigate the risks?
Answer options
- A. How the response will affect the quality of the components
- B. Verify due dates for the actions have been identified
- C. Probability of a response triggering a secondary risk
- D. If the risk response is tied to an activity on the critical path
Correct answer: D
Explanation
The correct answer is D because understanding whether the risk response is linked to a critical path activity is essential for prioritizing actions that could impact the project's timeline. Options A, B, and C are also important considerations, but they are secondary to the critical path's influence on project success.