A mobile operator wants to test a new network prototype before conducting full implementation on the entire network. What type of risk response strategy did the mobile operator choose?

Answer options

Correct answer: B

Explanation

The correct answer is B, Mitigate, as testing a prototype allows the operator to identify and reduce potential risks before full implementation. The other options do not fit; Transfer would involve shifting the risk to another party, Avoid would mean not pursuing the prototype at all, and Accept would indicate a willingness to take on the risks without testing.