The risk manager is about to go on medical leave, but before departing, conducts a risk response planning review meeting with stakeholders. A new risk manager is assigned to the project, and during the first status meeting an issue is identified.
What is the appropriate course of action in this case?
Answer options
- A. Perform a project review.
- B. Perform a risk reserve analysis.
- C. Implement an action plan to resolve the issue.
- D. Delegate to the action owner.
Correct answer: C
Explanation
The correct answer is C because it is essential to take immediate action to address the identified issue. Options A and B do not directly resolve the issue, and option D may not be appropriate if the new risk manager is responsible for the resolution.