PMI Risk Management Professional (PMI-RMP) — Question 22
A common understanding of the value of risk management among key stakeholders is an effective foundation to managing risk effectively. The project manager should ensure training is provided to which of the following groups to create this understanding?
Answer options
- A. Project team members and customers
- B. Management and external stakeholders
- C. Management and customers
- D. Project team members and management
Correct answer: D
Explanation
The correct answer is D, as training project team members and management ensures that those directly involved in the project and those making strategic decisions understand risk management. Option A misses management's critical role, option B includes external stakeholders who may not be directly involved, and option C excludes project team members who need to be aligned with management's understanding.