PMI Risk Management Professional (PMI-RMP) — Question 21

A newly assigned project manager is reviewing the project documents with stakeholders to identify opportunities that will fast track the project and realize the financial benefits of early completion. What document should be updated at the end of the review?

Answer options

Correct answer: A

Explanation

The correct answer is A, as the risk register should be updated to reflect any new risks or changes in the project's risk landscape identified during the review. The other options, while related to risk management, do not specifically serve as a repository for current risks, making them less relevant for this task.