PMI Risk Management Professional (PMI-RMP) — Question 157

A risk manager has been assigned to a new project and learns that stakeholders and project team members are spread across multiple time zones. Furthermore, many project team members have not worked together in the past. These items are identified as potential risks and added to the risk register.

How should the risk manager improve collaboration during risk planning?

Answer options

Correct answer: B

Explanation

The correct answer is B because creating a repository allows all team members to access necessary documents and artifacts, which is crucial for effective collaboration, especially across time zones. Option A, while helpful, may not be feasible; option C focuses on metrics rather than collaboration tools; and option D, although useful for risk analysis, does not directly enhance collaboration among the team.