Multiple new risks have come up on a project that were not included on the risk register. The project manager met with the team to explain that risk management is critical for the success of the project, and risk identification is key.

What should the project manager do next?

Answer options

Correct answer: A

Explanation

The correct answer is A because reviewing assumptions and constraints helps to understand the context of the risks better. Options B, C, and D, while related to risk management, focus on processes and actions that should occur after a thorough understanding of existing assumptions and constraints has been established.