PMI Risk Management Professional (PMI-RMP) — Question 122
During a project review meeting, an executive scrutinizes the risk section, including risks on the watch list, and demands action to close them out.
What is the executive's risk attitude?
Answer options
- A. Averse
- B. Seeking
- C. Neutral
- D. Tolerant
Correct answer: A
Explanation
The executive's insistence on taking action to mitigate risks indicates a risk-averse attitude, as they are not comfortable with unresolved risks. The other options imply different attitudes: 'Seeking' suggests a desire to take on more risk, 'Neutral' indicates indifference, and 'Tolerant' means accepting risks without urgency to address them.