PMI Risk Management Professional (PMI-RMP) — Question 122

During a project review meeting, an executive scrutinizes the risk section, including risks on the watch list, and demands action to close them out.
What is the executive's risk attitude?

Answer options

Correct answer: A

Explanation

The executive's insistence on taking action to mitigate risks indicates a risk-averse attitude, as they are not comfortable with unresolved risks. The other options imply different attitudes: 'Seeking' suggests a desire to take on more risk, 'Neutral' indicates indifference, and 'Tolerant' means accepting risks without urgency to address them.