PMI Risk Management Professional (PMI-RMP) — Question 120
Which of the following would a proactive risk manager do during the Monitoring and Controlling Process?
Answer options
- A. Develop risk responses, create risk management plan, and stay alert for risk events.
- B. Update the lessons learned documents, develop risk responses, and create the risk management plan.
- C. Review identified risks, stay alert for risk events, and remind team members to keep the risk manager informed about risk triggers.
- D. Review lessons learned document to identify risks, quantify risks, and lower impact ratings.
Correct answer: C
Explanation
The correct answer, C, highlights the importance of reviewing identified risks and ensuring communication about risk triggers, which is crucial for proactive risk management. Options A and B focus on development tasks rather than monitoring, while D emphasizes quantifying risks, which is not the primary focus of the Monitoring and Controlling Process.