PMI Risk Management Professional (PMI-RMP) — Question 120

Which of the following would a proactive risk manager do during the Monitoring and Controlling Process?

Answer options

Correct answer: C

Explanation

The correct answer, C, highlights the importance of reviewing identified risks and ensuring communication about risk triggers, which is crucial for proactive risk management. Options A and B focus on development tasks rather than monitoring, while D emphasizes quantifying risks, which is not the primary focus of the Monitoring and Controlling Process.