PMI Professional in Business Analysis (PMI-PBA) — Question 97

The stakeholders for a newly approved project are subject matter experts who are very knowledgeable in the client’s business and will provide the project requirements. The project team scheduled separate sessions with each subject matter expert to identify and prioritize the requirements.
Which technique is being used?

Answer options

Correct answer: D

Explanation

The correct answer is D, as idea and mind mapping involve visually organizing information and requirements, which is useful when working with subject matter experts. Options A and C do not specifically focus on individual contributions in a structured manner, while B, the Delphi technique, emphasizes anonymous feedback rather than direct interaction.