PMI Professional in Business Analysis (PMI-PBA) — Question 93
A company is working on the next big release of their best-selling product. The requirements will be validated through in-person validation sessions.
What would be the most viable technique to use in this scenario?
Answer options
- A. A use-case development session
- B. A review of the previous version
- C. A review of the solution prototype
- D. A brainstorming session
Correct answer: A
Explanation
The most suitable technique in this context is 'A use-case development session' because it allows for detailed exploration of user interactions and requirements in a collaborative environment. The other options, such as reviewing previous versions or prototypes, may not provide the immediate feedback and engagement needed during in-person sessions.