PMI Professional in Business Analysis (PMI-PBA) — Question 83

A business analyst has started a project for a system enhancement. In order to determine how the requirements will be approved, the business analyst schedules a meeting with the stakeholders to discuss the proposed approval process.
Which measure of effective decision making allows the business analyst to finalize the process for requirement approval?

Answer options

Correct answer: A

Explanation

The correct answer is A because documenting the requirements validation process ensures that all requirements are assessed and agreed upon, which is crucial for approval. The other options refer to different stages of requirement handling: elicitation focuses on gathering information, verification deals with confirming the correctness of the requirements, and approval specifically pertains to the final agreement on those requirements.