PMI Professional in Business Analysis (PMI-PBA) — Question 82
What are some of the components of a requirements management plan?
Answer options
- A. Requirements work plan, prioritization process, and traceability matrix template
- B. Requirements definition, functional and non-functional requirements, and decision-making process
- C. Requirements definition, requirements attribute template, and traceability matrix template
- D. Requirements work plan, requirements definition, and traceability matrix template
Correct answer: C
Explanation
The correct answer, C, accurately lists components that are essential for managing requirements effectively, including a requirements attribute template that helps in documenting specific characteristics of requirements. Options A, B, and D contain elements that, while relevant to requirements management, do not fully align with the key components specified by the requirements management plan.