PMI Professional in Business Analysis (PMI-PBA) — Question 76

A business analyst has been assigned to a project team that is redesigning the company’s website. The business analyst has been documenting the relationships between requirements and has found requirements that do not trace to a business need.
Which type of requirements are these?

Answer options

Correct answer: B

Explanation

The correct answer is B. Out-of-scope requirements are those that do not align with the project's objectives or business needs, making them irrelevant to the current project. The other options, such as Tested, Implemented, and In-scope, all refer to requirements that are either completed or aligned with the project goals.