PMI Professional in Business Analysis (PMI-PBA) — Question 64

The requirements baseline is ready for sign-off when the requirements are:

Answer options

Correct answer: D

Explanation

The correct answer is D because it emphasizes that requirements must be clear and consistent, as well as complete and validated to ensure they are understood and agreed upon. The other options, while mentioning important aspects, do not fully encompass all necessary criteria for a sign-off.