PMI Professional in Business Analysis (PMI-PBA) — Question 55

Company A has initiated a project to update their online ordering system. The business analyst has noticed that the purchasing department, a primary stakeholder, is excluded from the list of stakeholders.
In which reference material can the business analyst find information about the missing project stakeholders?

Answer options

Correct answer: C

Explanation

The correct answer is C, the Organizational chart, as it typically outlines the structure of the organization, including key stakeholders. The other options, such as the Business analyst communication plan, Business case, and Business analysis plan, may not provide a clear view of the stakeholder relationships and roles within the project.