PMI Professional in Business Analysis (PMI-PBA) — Question 48
A business analyst assigned to review test output for a project realizes that an approved requirement has been missed. Which technique could the business analyst have used to ensure that requirements were delivered as stated?
Answer options
- A. Use cased
- B. Requirements management plan
- C. Traceability matrix
- D. Work breakdown structure
Correct answer: C
Explanation
The correct answer is C, the Traceability matrix, which helps ensure that all requirements are tracked throughout the project lifecycle, linking them to their respective test cases. The other options do not specifically provide a method for tracking and verifying requirements against test results, making them less suitable for this scenario.