PMI Professional in Business Analysis (PMI-PBA) — Question 136
Requirements for a project have already been approved and finalized when a stakeholder approaches the project team with a change to one of their requirements. Which method of document control should the business analyst use to document changes in requirement(s) versioning?
Answer options
- A. Project plan
- B. Statement of work
- C. Traceability matrix
- D. Problem or opportunity statement
Correct answer: C
Explanation
The Traceability matrix is the correct choice because it tracks the relationship between requirements and their changes, allowing for effective version control. The Project plan and Statement of work serve different purposes related to project management and scope, while the Problem or opportunity statement focuses on identifying issues rather than tracking requirement changes.