PMI Professional in Business Analysis (PMI-PBA) — Question 112

The business analyst has been assigned to a project which delivers functionality for a much larger solution. The project has many requirements but has not received adequate funding. In addition, the stakeholders’ views conflict.
Which tools and techniques should the business analyst use to maximize business value while establishing the requirements baseline?

Answer options

Correct answer: C

Explanation

The correct answer is C because a weighted matrix helps prioritize requirements based on their value, while process flows provide a visual representation of processes and organizational charts clarify stakeholder roles. The other options include tools that are less effective in aligning conflicting stakeholder views and prioritizing requirements under funding constraints.