The business analyst is planning an approach to formally manage updates to requirements that may be requested by stakeholders. What should the business analyst do?
Answer options
- A. Document changes as they occur.
- B. Obtain approval from the project sponsor.
- C. Develop a change control process.
- D. Hold firm on scope and reject changes.
Correct answer: C
Explanation
The correct answer, C, is appropriate because developing a change control process allows for a structured approach to managing requirement changes, ensuring that all modifications are evaluated and approved systematically. Options A and D are reactive and do not provide a formal method for managing changes, while B, while important, does not encompass the entire process needed for managing updates effectively.