PMI Professional in Business Analysis (PMI-PBA) — Question 100

Change control systems include provisions to implement changes without formal review in the event of an emergency. When the provision is utilized:

Answer options

Correct answer: A

Explanation

The correct answer is A because even in emergencies, proper documentation of changes is essential for accountability and tracking. Option B is incorrect as evaluating risks is a fundamental part of the change control process, and not being evaluated is a flaw. Option C is not applicable in an emergency scenario where immediate action is needed, and option D contradicts best practices since managerial oversight is important, even during emergencies.