Change control systems include provisions to implement changes without formal review in the event of an emergency. When the provision is utilized:
Answer options
- A. changes must still be documented and captured.
- B. the risk associated with the change is not evaluated.
- C. a change control board should be established.
- D. changes can be applied without further managerial involvement.
Correct answer: A
Explanation
The correct answer is A because even in emergencies, proper documentation of changes is essential for accountability and tracking. Option B is incorrect as evaluating risks is a fundamental part of the change control process, and not being evaluated is a flaw. Option C is not applicable in an emergency scenario where immediate action is needed, and option D contradicts best practices since managerial oversight is important, even during emergencies.