PMI Agile Certified Practitioner (PMI-ACP) — Question 99
During an iteration review, the agile team asserts that a product is complete because development and review were finished. The product owner disagrees, since the product has not been tested.
What should the agile practitioner do?
Answer options
- A. Work with the agile team and product owner to agree on the definition of done
- B. Ask the sponsor to determine whether the product is completed
- C. Plan another review after the product has been tested
- D. Add testing to the backlog, and have the product owner reprioritize
Correct answer: A
Explanation
The correct answer is A because the agile practitioner should facilitate a discussion between the agile team and the product owner to create a shared understanding of what 'done' means, which typically includes testing. Options B and C are not proactive in resolving the disagreement, and D does not address the need for a clear definition of done, which is essential for Agile development.