PMI Agile Certified Practitioner (PMI-ACP) — Question 100
A project team meets to estimate user stories for a sprint. While an important non-functional requirement must be delivered in the sprint, the estimate exceeds sprint capacity.
What should the team do?
Answer options
- A. Estimate only functional requirements that will impact product quality
- B. Add team resources
- C. Refer the issue tot eh product owner
- D. Break non-functional requirements into those that can be delivered in the given sprint
Correct answer: C
Explanation
The correct answer is C because involving the product owner allows for prioritization and potential adjustment of requirements based on the team's capacity. Options A and D do not address the need to manage the non-functional requirement appropriately, while B may not be feasible or effective in resolving capacity issues.