PMI Agile Certified Practitioner (PMI-ACP) — Question 9

During a planning session, four out of five team members vote to include eight story points in a particular story, while the fifth member votes for five story points.
How should this be handled?

Answer options

Correct answer: C

Explanation

The correct answer is C because it encourages collaboration and aims to resolve differences by facilitating a discussion to reach a consensus. Option A ignores the concerns of the minority, while B postpones resolution without addressing the disagreement. Option D incorrectly places the decision-making responsibility on the customer, rather than the team.